A test manager is reviewing the test dashboard at the midpoint of system testing. The dashboard shows: - Test case execution: 50% complete (on schedule) - Defect open/close ratio: 3:1 (three new defects opened for every one closed) - Critical defects open: 12 (increasing trend) - Test environment downtime: 15% of available time Which combination of test control actions is MOST appropriate?